[ Accessibility | Jump to content]
View Map
X

News








All Hazard Activity News

Clear

Pipeline Survey - SEAL



The Ocean Infinity vessel Armada 78-04 (Call Sign: 9V8530) will be carrying Pipeline Inspection Operations between / along the locations noted below:


The Ocean Infinity vessel Armada 78-04 (Call Sign: 9V8530) will be carrying Pipeline Inspection Operations between / along the locations noted below:

See detailed map on our bulletin website

Show More

DSV Decommissioning - B-Block Balmoral template



The DSV Topaz will be completing decommissioning activities at B-Block. The vessel will be at B-Block from the 13th May for ~ 30 days.


The DSV Boka Topaz is due to mobilise to execute the Decommissioning scopes at B Block within the Central North Sea. The vessel will be working at B-Block 500m safety zones. Upon completion of the offshore campaign, the vessel will demobilise in Aberdeen. 

See detailed map on our bulletin website

Show More

Subsea campaign to disconnect and remove Sean Field pipelines and subsea infrastructure



The project is to remove 20” and 30” pipeline tie-in spools, the Sean RD power cable, the SSIV and protection frame, the SSIV umbilical and the mooring buoys using vessels Edda Freya and Olympic Ares. Starting 7th June 2026.


As part of field decommissioning operations, the following field infrastructure will be removed using two vessels Edda Freya and Olympic Ares over two months.

•            Tie in spools from PL310 (Sean Papa to Sean Romeo production flowline)

•            Tie in spools from PL311 (Sean Papa to SSIV to Bacton production flowline)

•            PLU5156 (Sean Papa to Sean Romeo power cable; 4.89 km in length)

•            PLU5157 (367 m Sean Papa to SSIV hydraulic umbilical; 367 m in length)

•            SSIV

•            Mooring buoys

In order to gain access to the pipeline ends, a dredger will be employed to gain access to the ends for cutting.  Two 20” tie-in spools of PL310 (41 m section at the Sean Romeo end and 50 m section at the Sean Papa end), three 30” tie-in spools (two 10 m sections at the SSIV end and one 65 m at the Sean Papa end) will then be cut and recovered.  The pipeline spools will be recovered to the vessel deck in 10 m sections.   Once recovered, the remaining pipeline ends will be remediated with two tonne rock bags. 

See detailed map on our bulletin website

Show More

Geotechnical Survey - Kyla Field (Previously Part of Kyle Field)



Fugro Revelation to undertake geotechnical survey at seventeen (17) locations within Kyla Field


Vessel to be on location for approx eight (8) days.

 

No streamers to be towed for this survey.

See detailed map on our bulletin website

Show More

Geotechnical Survey - Bruce Field



Fugro Revelation to undertake geotechnical survey at three (3) locations within Bruce Field


Vessel to be on location for approx four (4) days.

 

No streamers to be towed for this survey.

See detailed map on our bulletin website

Show More

Geotechnical Survey - Skerryvore Field



Fugro Revelation to undertake geotechnical survey at four (4) locations within Skerryvore Field


Vessel to be on location for approx four (4) days.

 

No streamers to be towed for this survey.

See detailed map on our bulletin website

Show More

Infill Drilling - Cygnus Field



The Valaris Norway is adjacent to the Cygnus Alpha, operating within the 500m zone. Anchors may extend beyond this point. *Please note that there is a slight delay between Cygnus A and Valaris Norway navigational aid activation, following assessment a dispensation has been approved under CL/63/8*


Show More

Infill Drilling - Cygnus Alpha



The Valaris Norway is located adjacent to the Cygnus Alpha Wellhead platform and will be operating within the 500m zone. Anchor's may extend beyond this point. *Please be advised that there is a slight delay between Cygnus A and Valaris Norway and Navaid lights activation. An approved dispensation is in place under CL/63/8*


Show More

Nearshore UXO Identification Dive Survey - Curtis Marshall



Mariners are advised that the Northern Endurance Partnership (NEP) will be undertaking a nearshore Unexploded Ordnance (UXO) investigation survey in the southern North Sea, utilising divers. The survey will be conducted by the vessel DSV Curtis Marshall.


Mariners are advised that the Northern Endurance Partnership (NEP) will be undertaking a nearshore Unexploded Ordnance (UXO) investigation survey in the southern North Sea, utilising divers. The survey will be conducted by the vessel DSV Curtis Marshall (see section 6)

The scope will include targeted investigation of potential UXO targets within NEP Pipeline and Cable Construction Area Block 1 (see Figure 1 and Table 1 below) in water depths of ≤10 m. Where required, clearance activities will be undertaken. Clearance methods may include deflagration (low-order disarming), and the relocation of debris away from the pipeline route and associated exclusion zone. In addition, the vessel will undertake nearshore sediment sampling within the same work area. Relevant permissions in place are provided in Section 2.

The vessel is estimated to arrive on location on 17thApril 2026.The investigation is expected to take ~14 days to complete (weather dependant). Mariners are advised to maintain a safe distance (of at least 500m) from the survey vessel locations at all times.

For further information, contact details for the Fishing Industry Representative and the Company Fisheries Liaison Officer are provided in Section 7.

See detailed map on our bulletin website

Show More

Hook-up and tensioning of Rosebank FPSO mooring lines



3 x anchor handling vessels (AHVs) will hook-up and tension 12 x mooring chains to secure the Rosebank FPSO in location. This will be followed by cutting off the excess mooring chain and recovering to deck. Part of this scope will be to recover blast matts & turning bollards.


Skandi Vega / Skandi Iceman & Skandi Skansen will conduct operations to hook-up 12 x mooring chains to the Rosebank FPSO when in location in the Rosebank field.

This will include tensioning of the mooring chains to establish 100 year storm safe.

Following this the excess mooring chain will be cut and recovered to deck.

Survey activities is a part of this scope.

Part of this scope will be to recover blast matts & turning bollards.

Once 100 year storm safe is established the Skandi Vega & Skandi Iceman will leave the field, however Skandi Skansen will remain until scope complete.

See detailed map on our bulletin website

Show More

UXO Identification Survey - Liverpool Bay - Update



Mariners are advised that Liverpool Bay CCS Ltd will continue to conduct a survey activities using the Titan Discovery & Argyll Explorer


The Unexploded Ordinance (UXO) investigation will continue in the Eastern Irish Sea to identify potential UXO targets (pUXO) along the Liverpool Bay CCS Cable Construction Area (See Figure 1 and Table 1 within the attached notice)  

 

The UXO corridor has been divided into ten separate blocks listed Blocks A-J to enable clear engagement and communications to all relevant stakeholders. 

 

 Blocks A – J coordinates can be found Below  

                                                           

The Titan Discovery will predominantly work within Blocks I-J, the Argyll Explorer will concentrate work in Blocks A-D and later I-J. 

 

The positions of any targets identified as confirmed Unexploded Ordinance (cUXO) will be shared within a separate notice and posted as a hazard on the Kingfisher Bulletin Service.   

 

The Titan Discovery is estimated to be on location for a further 14 days (weather dependant) and the Argyl Explorer is estimated to be on location for a further 21 days (weather dependant)  

 

Mariners are advised to always maintain a safe distance (of at least 500m) from the Argyll Explorer, Titan Discovery. 

 

For further information, contact details for the Company Fisheries Liaison Officers are provided in Section 7 of the attached notice. 

 

 

See detailed map on our bulletin website

Show More

Navigational Aid Maintenance at the Banff and Kyle Field



Maintenance of the Navigational Aids (Cardinal Buoys) at the Banff and Kyle Field


Maintenance of the Navigational Aids (Cardinal Buoys) at the Banff and Kyle Field

See detailed map on our bulletin website

Show More

Rosebank FPSO station keeping



Once the Rosebank FPSO arrives on location within the Rosebank Development Area, the 4 x tug vessels will conduct station keeping of the FPSO whilst the mooring chain hook-up is completed.


The AHTS vessels:

Normand Prosper / Normand Sapphire / Skandi Minder / Skandi Saltfjord

are conducting the tow from Bergen, Norway of the Rosebank FPSO to the Rosebank Oilfield.

Once on location at the Rosebank field, all 4 vessels will conduct station keeping until the mooring chain hook-up is complete.

Details of AHTS conducting the hook up of anchors can be found in the Notice Titled - Hook-up and tensioning of Rosebank FPSO moorings

See detailed map on our bulletin website

Show More

Leman Southwest Pipelines PL3731 & PLU3732 Disconnect Campaign



Leman Southwest Pipelines PL3731 & PLU3732 Disconnect Campaign


Perenco UK Limited is carrying out a pipeline disconnection (PL3731 & PLU3732) campaign using the Wagenborg Kingsborg The Kingsborg will act as the Diving Support Vessel (DSV) and will be on location in to carry out the pipeline disconnect activities using divers in 24hr operations. The pipeline disconnect campaign is scheduled to take place over a 10 days period. 

See detailed map on our bulletin website

Show More

Rigmove Irish Sea Pioneer - Lennox Standby to Port of Blyth-DELAYED



Irish Sea Pioneer Rig move - Lennox Standby to Blyth under tow by Tug vessel 'Boka Summit'-DELAYED


Irish Sea Pioneer is moving from Lennox Stanby position (Liverpool Bay) under tow to Blyth by the Tug 'Boka Summit'.

See detailed map on our bulletin website

Show More

ROV survey of Gassco operated pipelines in UKCS - Langeled South, Vesterled,Gjoa gas, Utsira high



ROV survey of UKCS sections of pipelines for Langeled South, Vesterled, Gjoa gas export and Utsira high


Pipeline survey using ROV.

Base case vessel is “Reach Remote 1” which is an unmanned vessel with 24/7 manning onshore.

Vessel Reach Remote 1 - n.b this is an unmanned vessel

Call sign  JXMQ

Water depth: approx. 70-150 m

See detailed map on our bulletin website

Show More

Rig - Noble Resolute



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Show More

Rig - Valaris 120



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Show More

Rig - Deepsea Atlantic



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Decommissioning Works - North Cormorant



The CSV Oceanic is currently on site, carrying out Top Side preparation activities as part of the removal process for the Top Side of the installation. Once these preparation works are completed, the Pioneering Spirit will be mobilised to attend and execute the actual removal of the Top Side.


The CSV Oceanic will be carrying out the first stage of work within the North Cormorant 500m Zone, and I’d like to highlight that there is a dedicated ERRV in place to support the entire workscope. Once these preparation activities are completed, the Pioneering Spirit will attend to remove the topside as planned.

See detailed map on our bulletin website

Show More

Decommissioning preparation works - Eider Alpha



The Eider Alpha upper jacket will have a construction vessel and ERRV working inside the 500m zone conducting preparation works for upper jacket removal by HLV at latter end of working window provided.


Show More

Decommissioning Geophysical Surveys - Devenick, Central Brae, West Brae & Braemar Fields



Mariners are advised that Gardline will be conducting geophysical surveys at Devenick, Central Brae, West Brae and Braemar fields with environmental sampling covering these site and East Brae, Brae Alpha and Brae Bravo. The surveys will be carried out by the Kommandor (IMO 8517205) from the 1st April 2026 lasting approximately 45 days.


Show More

Survey - Captain Riser Replacement Project



Survey of the area required for the captain riser replacement project.


Show More

Rig Placement and Environmental survey - Captain Area B and C and will include Captain B15



In preparation for upcoming wells activity. Ithaca are planning Environmental survey's at Captain Area B and C and will include Captain B15. The following Quadrant/Blocks are included: 13/22 13/23 13/18 13/17 13/16 13/21


Ithaca is planning to conduct a bathymetry, debris clearance, habitat assessment and environment baseline survey in the Captain Field (over Areas B & C). The scope of the survey work will involve collection of SSS, SBES, MBES and  passive magnetometer data. Video and stills photography will be undertaken at a number of environmental stations followed by grab samples.

See detailed map on our bulletin website

Show More

Survey prior to Tybalt P&A activities



In preparation of plug and abandonment of wells 211/8c-5 and 211/8c-4z. Survey will comprise: side scan sonar (SSS) and mutli-beam echo sounder (MBES), drop camera/video.


Show More

Environmental Survey - Causeway Fionn



A re-visit of the 2020 pre-decommissioning survey locations at Causeway-Fionn.


Survey will comprise:SSS/MBES of well areas,drop camera/video,grab sampling for chemical and faunal analyses

See detailed map on our bulletin website

Show More

Seismic Survey PGS26001 in the Norwegian sector



R/V Ramform Atlas will conduct a seismic survey east of the Ekofisk and Valhall oilfields from 5 May to 15 June 2026. Ramform Atlas will deploy 16 streamers, each 7,050 meters long, with a towing width of approximately 1,600 meters. All fishing vessels planning to operate in the survey area are requested to contact the Fisheries Liaison Officer (FLO) on board Ramform Atlas.


All fishing vessels planning to operate in the survey area are requested to contact the Fisheries Liaison Officer (FLO) on board Ramform Atlas. Thor Alpha and Thor Omega are support vessels.   For more info, please contact Ramform Atlas or the support vessels on VHF ch 16 or 72 (working channel) FLO on email: bjarniba (at) gmail . com FLO on WhatsApp +47 413 97 983  

See detailed map on our bulletin website

Show More

GI2P Development Project - Pierce Field



The GI2P project is to change the A2y and A4 existing wells at the Pierce field, from Gas Injection Wells to Gas Producer wells. ** Vessel - Deep Discoverer **


For A4, this involves disconnecting the well from the Gas Injection / Lift system at the MDS manifold, and tying the well back to the production system, teeing into the A14/A6 production system (PL4863) at the MDS.  6” rigid spools shall be installed and leak tested. For A2y, this involves disconnecting the well from the Gas Injection / Lift system, and tying the well back to the production system, teeing into the A12/A1 production system (PL4004) at the A12 T-piece. 6” rigid spools shall be installed and leak tested. Gas Lift supply is to be maintained by connecting together the 2.5-inch (PL2858) and 6-inch (PL4813) flexibles (previously disconnected from A2y) using a 1.5m long, 6”x2.5” reducing spool. These flanged connections shall be leak tested.

See detailed map on our bulletin website

Show More

Pre-laying of anchors at Falcon - in preparation for Noble Patriot arrival



Pre-laying of anchor at Falcon - in preparation for Noble Patriot arrival, as detailed within WIA/1885 CL/1588. 8 x anchors to be placed within radius of 61 19 50.08 North 00 59 28.19 East.


Pre-laying of anchor at Falcon - in preparation for Noble Patriot arrival, as detailed within WIA/1885 CL/1588.8 x anchors to be placed within radius of 61 19 50.08 North 00 59 28.19 East.

See detailed map on our bulletin website

Show More

Plug & Abandonment Operations at Cladhan - Noble Patriot



Plug and abandonment operations at Cladhan - to be completed by Noble Patriot, as detailed within WIA/1885 CL/1588. Including 8 x anchors within radius of 61 08 53.92 North 00 47 13.62 East.


Plug and abandonment operations at Cladhan - to be completed by Noble Patriot, as detailed within WIA/1885 CL/1588.Including 8 x anchors within radius of 61 08 53.92 North 00 47 13.62 East.

See detailed map on our bulletin website

Show More

Dana Diving Operations in the Triton Area



Dana will have the DSV Seven Kestrel diving within the Triton FPSO 500m zone and at the Guillemot West locations for 2 to 3 days, weather depending.


Divers will be carrying out electical diagnotices at Triton and Guillemot West locations 

See detailed map on our bulletin website

Show More

Arrival of Petrojarl Rosebank FPSO at the Rosebank Field



The Petrojarl Rosebank FPSO will arrive on station at the Rosebank Field at the earliest on the 25th of May 2026.


The Petrojarl Rosebank FPSO will arrive on station at the Rosebank Field at the earliest on the 25th of May 2026 for hook up and commissioning ready for full production at the end of 2026.

See detailed map on our bulletin website

Show More

Survey - Brent Field Attic Oil Recovery



Brent Charlie Attic Oil Recovery


The 2026 Attic Oil Recovery (AOR) campaign at Brent Charlie will encompass an upfront access and survey campaign followed (as required / possible) by recovery of mobile attic oil and interphase material.

See detailed map on our bulletin website

Show More

Confirmed Unexploded Ordnance NEP Construction Area - Block 5



Mariners are advised that following a UXO identification survey the vessel Olympic Taurus has identified a second confirmed UXO within Block 5of the NEP Construction Area. Further investigations are being conducted and updates will follow.


Show More

Confirmed Unexploded Ordnance NEP Construction Area - Block 3



Mariners are advised that following a UXO identification survey the vessel Olympic Taurus has identified a confirmed UXO within Block 3 of the NEP Construction Area. Further investigations are being conducted and updates will follow.


Show More

NEP Endurance Area - Passive Acoustic Monitoring (PAM) Servicing and Seabed Lander deployment



The Acoustic Spatial Capture- Re-Capture (ASCR) Array has now been temporarily removed for servicing and will be redeployed during this tranche of work (As-Laid coordinates will follow) An additional 2 Seabed Landers will be deployed within the Cardinal Buoys (Figure 1 and Table 2) The deployment will be carried out by the by the BB Ocean estimated to take place ~ 2nd May 2026. These landers will only be deployed for 7 days (weather dependent) and will be marked by surface floats.


Mariners are hereby advised that the Northern Endurance Partnership (NEP) is continuing to undertake an Offshore Passive Acoustic Monitoring (PAM) Survey within the Southern North Sea. This survey deployed of a series of PAM moorings to support ongoing environmental monitoring activities.  

The Acoustic Spatial Capture- Re-Capture (ASCR) Array has now been temporarily removed for servicing and will be redeployed during this tranche of work (As-Laid coordinates will follow)  

An additional 2 Seabed Landers will be deployed within the Cardinal Buoys (Figure 1 and Table 2 of the attached notice) The deployment will be carried out by the by the BB Ocean estimated to take place ~ 2nd May 2026. These landers will only be deployed for 7 days (weather dependant) and will be marked by surface floats.  

 

Seabed moorings and Cardinal buoys remained in their original positions after servicing. Current positions of equipment are provided below.

 All moorings will remain in place throughout the remaining ~5-month monitoring period. 

 A full list of equipment details will be provided within the next notice once As-Laid positions are confirmed. 

Coordinates are provided in Table 1 and Table 2 and are illustrated in Figures 1 and 2 within the attached notice. 

Mariners are advised to maintain a safe distance from the deployment locations at all times. 

For further information, contact details for the Fishing Industry Representative and the Company Fisheries Liaison Officer are provided in Section 7 of the attached notice. 

See detailed map on our bulletin website

Show More

Decommissioning - Amethyst A1D



The OBANA Heavy Lift Vessel will undertake jacket removal activities at the Amethyst A1D.


Show More

Diving Operations to Installation of Pipe Spool and Tie In at BP WOSPS Location



Diving operation to install pipe spool / tie in assembly header into existing system – BP WOSPS location


THe Vessel Deep Arctic will conduct diving operations at the BP WOSPS T location in 130m water depth to install a 40m (approx.) pipe spool & tie in assembly header into the existing West Of Shetland Pipeline System (WOSPS) and install GRP cover protection over the newly installed equipment. 

See detailed map on our bulletin website

Show More

NEP - Offshore ROV, UXO ID & Clearance - Glomar Wave



Mariners are advised that the Northern Endurance Partnership (NEP) offshore Unexploded Ordinance (UXO) Investigation & Clearance, within the southern North Sea has resumed, the Glomar Wave will now continue the investigation. A n NFFO OFLO is now onboard to monitor fishing activity.


Mariners are advised that the Northern Endurance Partnership (NEP) will be undertaking an offshore Unexploded Ordinance (UXO) Investigation survey utilising an ROV (Remote-Operated Vehicles) within the southern North Sea. The survey is being conducted by the vessel Glomar Wave (see section 6 in the attached notice) and has been extended for a further 25 days due to weather conditions.  

 

The survey will carry out targeted investigations of potential UXO targets and conduct clearance of the targets if required within NEP Pipeline and Cable Construction Area Blocks 1 to 5 (See Table of coordinates ) >10m water depth. The position and extent of the NEP Pipeline and Cable Construction Area Blocks are currently under review and will be updated once the review is complete.   

 

The positions of any targets identified as potential Unexploded Ordinance (pUXO) will be shared within a separate notice and posted as a hazard on the Kingfisher Bulletin Service.   

 

The vessel has made a port call and a NFFO OFLO is now onboard to monitor fishing activities (contact details in section 7 of the attached notice) 

 

Mariners are advised to maintain a safe distance (of at least 500m) from the vessel at all times. 

 

For further information, contact details for the Fishing Industry Representative and the Company Fisheries Liaison Officer are provided in Section 7 of the attached notice. 

See detailed map on our bulletin website

Show More

Swift 10 MODU on location on the Sean Papa Platform.



The Swift 10 is contracted to ONE-Dyas to plug and abandon wells on the Sean Papa platform as part of the Sean Field decommissioning in the Southern North Sea for approximately 120 days. The rig is currently on location at Sean Papa (UKCS) all navigation aids are showing unsynchronised and Navigation lights and Fog signals higher than 35 meters MHWS.


The Swift 10 will arrive arround January 27th to Plug and Abandon the wells and pull the conductors on the Sean Papa manned platform.  The platform and rig will work in combined operation.The process will involve the MODU being towed to location, it will be  positioned temporarily at stand-off position then anchors will be run to move MODU into final position.

The Swift 10 is a MSC SEA-2750 self-elevating unit .  Aids to Navigation are listed as:- AIS, DSC MF/HF, VHF System, ER VHF Portable and RT/DSC, EPIRB,GPS/DGPS, Inmarsat C/ECG, GMDSS PRINTER, VSAT, LRIT, NAVTEX, SART, SSAS

The Rig Move procedure is in conjunction with the Marine Operations manual.  Required rig move notifications will be made prior to the move. 

The navigation lights on the Swift 10 are not able to be synchronised with the Sean PP. Navigation lights for both the Swift 10 and Sean Papa platform will remain turned on.On Swift 10 Navigation lights and Fog signals higher than 35 meters MHWS.

 

 

 

See detailed map on our bulletin website

Show More

OBN survey VIR26001 – Frigg



Viridien is planning to undertake an ocean bottom node (OBN) survey over the Frigg field area in both Norway and UK waters from 1st May until mid-August for up to 110 days. The survey will cover UKCS blocks 3/30, 4/46, 9/5, 9/10, 10/1 & 10/6 and Norway blocks 25/1-2 & 30/10-11.


This OBN survey will utilise three vessels: Siddis Mariner (node handling), Sanco Sword (seismic source) and Tanux III (support vessel).

 

Siddis Mariner will deploy acoustic sensors (nodes) using ROV’s on the seafloor around the Odin and Frigg fields, starting at the northern edge of the survey area. The nodes will be deployed 200m apart in lines up to 25km in length, with a line separation of 200m. Up to 25 lines of nodes are deployed at once.

 

Working in tandem with the Siddis Mariner, Sanco Sword will deploy a 200m towed 800 cubic inch seismic source up to 5km around and over the deployed node patch in an east / west direction, gradually moving southwards with each line. Once a node line has been covered by the seismic source, each node is recovered by ROV and processed for use on another section of the survey.

 

Tanux III will act as the support vessel for both Siddis Mariner and Sanco Sword.

 

Please note that the area defined in this notification will not be restricted in its entirety to fishing vessels for the duration of the survey. The rolling node area will only restrict access to a smaller section. FLOs will be placed on board Siddis Mariner and Sanco Sword to assist with fisheries on site.

 

Siddis Mariner: Call Sign LAIY3, IMO 9475181, captain@mariner.ohmeling.no, Tel +47 51 22 90 29

Sanco Sword: Call Sign ZDNE 7, IMO 9662100, Captain.sword@sanco.no, Tel +47 23 67 30 65

Tanux III: Call Sign V7MP4, IMO 9392406, Tanux3@uksnoy.no, Tel +87 07 73 23 14 41

See detailed map on our bulletin website

Show More

OBN survey EQ26009 - Martin Linge



OBN / Node-on-a-rope seismic survey over the Martin Linge Field. Up to 7700 seismic nodes are to be laid on the seabed. Please avoid this area while the survey is ongoing.


The OBN survey at Martin Linge will be carried out by the vessels REM Trader, Sanco Star, Esvagt Castor and Stålbas.

REM Trader will lay nodes on the seabed around the Martin Linge platform and Martin Linge FSO. The nodes are organised in a series of 27 lines in the NE-SW direction. On each line, there will be a node every 25m. Nodes lines are 400m apart.

When deploying the nodes, REM Trader will be very restricted in her manoeuvrability. She will have nodes, ropes and weights being deployed from her stern at a speed of 0.5-2 knots.

After nodes have been deployed Sanco Star will then deploy 2 seismic sources and fire shot points every 25m over the whole area at an average speed of 4.5 knots. Shot points are also fired along straight lines in the NE-SW direction. The source lines will be 100m apart. The towed equipment behind Sanco Star when acting as source vessel will measure approximately 200m x 100m (LxW).

Esvagt Castor and Stålbas will act as support and escort vessels for REM Trader and Sanco Star during the survey.

REM Trader: Call Sign 5BGQ5 - IMO 9529932 – captain@trader.remoffshore.no - +47 23 67 27 72

Sanco Star: Call Sign ZDIT8 – IMO 9410313 – captain.star@sanco.no - +47 23 67 85 50

Esvagt Castor: Call Sign OUKI2 – IMO 9508756 – castor@esvagtvessel.com - +45 61 62 67 74

Stålbas: Call Sign 5077682 – IMO LNXH – stalbas.bridge@besi.no - +47 90 68 88 37

See detailed map on our bulletin website

Show More

Acoustic Monitor - Culzean Field



In preparation for the installation of a floating Wind Turbine at Culzean - an acoustic device will be deployed near to the proposed wind turbine location at the Culzean field. The acoustic device will be at the location noted below - but will extend to a total height of 25m above the seabed. The device will deployed from 19th April 2026 (depending on weather) and will be in place for approx. six months.


In preparation for the installation of a floating Wind Turbine at Culzean - an acoustic device will be deployed near to the proposed wind turbine location at the Culzean field.  The acoustic device will be at the location noted below - but will extend to a total height of 25m above the seabed. The device will deployed from 19th April 2026 (depending on weather) and will be in place for approx. six months.  

See detailed map on our bulletin website

Show More

NEP Expansion Offshore Geophysical and Biological Survey



Mariners are advised that the Northern Endurance Partnership Expansion will be undertaking survey activities using the vessel Ocean Observer


Biological sampling will be preceded by geophysical investigations to select appropriate ground conditions for sampling. 

An NFFO Offshore Fisheries Liaison Officer (OFLO) will be onboard the Ocean Observer. Survey activities will be planned and work around static fishing gear to avoid disruption.    

The vessel is estimated to arrive on location ~21st April working 24 hours a day for ~ 58 days. 

Mariners are advised to politely maintain a safe distance (of at least 500m) from the Ocean Observer.

For further information, contact details for the Fishing Industry Representative and the Company Fisheries Liaison Officer are provided in Section 6 of the attached notice. 

See detailed map on our bulletin website

Show More

Decommissioning Activities - Grove G5, Seven Seas



Seven Seas - Wellhead protection structure at now removed and recovered to surface. Well subsea infrastructure still in place. 500 m safety zone remains in place. Grove G5 - Xmas tree and Wellhead protection structure remain in place with Wellhead Protection Structure Top Canopy removed. 500 m safety zone remains in place.


Wellhead protection structure at Seven Seas now removed and recovered to surface. Well subsea infrastructure still in place. Well-Safe Protector mobilising 15th April 2026 from Aberdeen to complete full well P&A. This date is subject to change depending on weather and operational requirements.  500 m safety zone remains in place.

 

Grove G5 Xmas tree and Wellhead protection structure remain in place with Wellhead Protection Structure Top Canopy removed. 500 m safety zone remains in place. Well-Safe Protector is expected to be on location around mid May 2026 to complete full well P&A.  This date is subject to change depending on weather and operational requirements.

See detailed map on our bulletin website

Show More

ROV survey of Statfjord Intrafield Pipeline



Pipeline survey using ROV from Edda Flora of the Statfjord intrafield pipeline (SIPS)


Statfjord intrafield survey using ROV from the vessel Edda Flora in water depths of approximately 70-150m. No towed equipment in use.

Vessel: Edda Flora

IMO/MMSI: 9386380/258245000

Call Sign: LAJW3

 

See detailed map on our bulletin website

Show More

Well Safe Defender in Magnus Field undertaking P&A Activities



Well Safe Defender will be locating to Magnus (South, F9 and F10 wells) location on or around 1 June to undertake P&A operations, for approximately 120 days. Anchors will be deployed upon arrival. 8 off anchors, each approx 1.2km from installation.


Show More

Rig Move - COSL Pioneer



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Shelf Drilling Winner



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - COSL Innovator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Deepsea Bollsta



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Seafox 7



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Deepsea Aberdeen



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Erda



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Disconnection of Christmas Trees (XT) at Strathspey Manifold Structure



CNRI plan to disconnect 12 subsea wells located at the Strathspey Production Manifold (SMS). The XT disconnections will be carried out by a Light Well Intervention Vessel (LWIV) , Seawell, using divers, as part of preparations for upcoming Plug and Abandonment (P&A) activities later in Q2 2026.


The proposed scope of work includes downhole flushing (no discharges to sea) of XT pipework and jumpers, disconnection of XTs, and performing barrier testing on isolation valves at each XT. 

In addition, PL870B (Water Injection Pipeline to Strathspey) will be disconnected at the SMS.

This is in preparation to support the final decommissioning at a later date.  

Location – 60 55 37.04 North, 01 42 18.26 East

See detailed map on our bulletin website

Show More

Free span - PL10 Ninian Pipeline System



Please be advised of potential hazard - Pipeline Free Span 52m in length (with one touch down point) Span height 0.5m


Show More

MNZ Survey - Liverpool Bay



As part of the MNZ project, Spirit Energy Resources Limited will utilise the Titan Endeavour to complete a geophysical and environmental survey along the proposed route from the Wirral coastline to an offshore crossover point.


The Titan Endeavour will be conducting MBES, sidescan sonar and magnetometer surveys along the intedned route. Environmental day grab and camera operations will be conducted at 1km intervals along the route.

See detailed map on our bulletin website

Show More

Rig Move and COMOPS Activity Notification - HAEVA JUB - Hoton Installation



Perenco are planning to undertake modifications to the topsides and install a conductor at Hoton utilising the HAEVA Jack-Up Barge (JUB). The HAEVA JUB will be positioned at Hoton, interfacing with the platform from the 5th April at the earliest (weather dependent).


Perenco are planning to undertake modifications to the topsides and install a conductor at Hoton utilising the HAEVA Jack-Up Barge (JUB). The HAEVA JUB will be positioned at Hoton, interfacing with the platform from the 5th April at the earliest (weather dependent). The Project is expected to last for a duration of 50 days. The HAEVA JUB occupies a much larger footprint that the Hoton installation, therefore, whilst the HAEVA JUB is on location, the HAEVA JUB Aids to Navigation (AtN) will be the sole AtNs for the duration of deployment and the Hoton platform will be blacked out. The positioning of the HAEVA JUB will require four mooring anchors which will be positioned at the following locations (ED50 UTM Grid Zone 31):

•    Starboard Bow: E 382 609, N 5 963 278•    Starboard Aft: E 382 056, N 5 962 750•    Port Aft: E 381 446, N 5 963 440•    Port Bow: E 382 038, N 5 963 924

Location Coordinates (WGS 1984):

Hoton: Latitude (WGS84):  53° 48' 10.0" N, Longitude (WGS84):  01° 12' 22.6" E HAEVA Working Position: 53° 48' 13.106" N, 001° 12' 28.308" E

See detailed map on our bulletin website

Show More

Well-Safe Protector - P&A Activities at Seven Seas and Grove G5



The Well-Safe Protector will mobilise from Aberdeen to the Seven Seas (48/7c-13y) location to undertake P&A activities, on or around the 15th April 2026. When complete, the rig will move to Grove G5 (49/10a-4) to complete P&A activities at this location. Total operations are expected to take 70 days and be complete by the end of July 2026.


The Well-Safe Protector will mobilise from Aberdeen to the Seven Seas (48/7c-13y) location to undertake P&A activities, on or around the 15th April 2026.  Operations are expected to take a total of 40 days and to be complete by the end of May 2026.  Following this activity, the rig will move to Grove G5 (49/10a-4) location to undertake P&A activities. It is expected to be at Grove G5 for 30 days.  All activities are expected to be complete by the end of July 2026. This date is subject to change depending on weather and operational requirements.

See detailed map on our bulletin website

Show More

Nearshore Dredging and Dredge Area Maintenance - Southern North Sea



Mariners are advised that the Northern Endurance Partnership (NEP) will be undertaking a nearshore dredging and dredge area maintenance campaign in the southern North Sea, utilising seven vessels. These vessels will be mobilising from the port of Hartlepool and working 24hrs a day.


Mariners are advised that the Northern Endurance Partnership (NEP) will be undertaking a nearshore dredging and dredge area maintenance campaign in the southern North Sea, utilising seven vessels. These vessels will be mobilising from the port of Hartlepool and working 24hrs a day.

The scope will include removal and temporary storage of dredge material within the NEP Pipeline and Cable Construction Area Block 1. Relevant permissions in place are provided in Section 2

The vessels are estimated to arrive on location on ~27 March 2026. Initial dredging activity is expected to take 71 ~ days to complete (weather dependant) and continued monitoring and maintenance of the dredge area will continue until pipelay activities begin. Updates will be issued via regular NEP Notice of Operations during the activity.

Mariners are advised to maintain a safe distance (of at least 500m) from vessel locations at all times.

For further information, contact details for the Fishing Industry Representative and the Company Fisheries Liaison Officer are provided in Section 7.

See detailed map on our bulletin website

Show More

Replacement of damaged tethered weather buoy - Rosebank Wave Rider Buoy



The vessel Deep Explorer will mobilise to be on location to recover the weather damaged buoy. The replacement buoy will be deployed at a new location as stated within this notice.


This notice is issued as a follow on to the active notice "Weather Buoy Installation – Rosebank Offshore Development Area" 

The vessel Deep Explorer will mobilise to the previously installed weather buoy location in order to recover the buoy, which has been weather damaged.Once recovered a replacement meteorological buoy will be deployed at a new location, as detailed below:

New Buoy Deployment Position:Latitude: 60° 00'.45.84" N Longitude: 003° 49'.27.89" W

All vessels are requested to maintain a safe distance from the Deep Explorer during recovery operations and from the replacement buoy once deployed.Once operations are complete, the original notice "Weather Buoy Installation – Rosebank Offshore Development Area" will be updated to reflect the new buoy position.

See detailed map on our bulletin website

Show More

Pressure testing of Gas Export Line System at the BP WOSPS location



The vessel Deep Explorer will be completing pre-commissioning activities – namely Pressure testing of Gas Export Line System – at the BP WOSPS location


Pressure testing of newly installed gas export pipeline

Connect downline from vessel into gas export PLEM and pressure test with filtered dyed seawater

See detailed map on our bulletin website

Show More

Preparation of and Removal of Offshore Installation Hewett 48/29A by Heavy Lift Vessels



Heavy Lift Vessels (HLVs) the Scaldis Rambiz and Gulliver will be mobilising the Hewett field to prepare the 48/29A Complex for removal. Once preparations have been completed the topsides and jackets will be removed and transported onshore for final disposal.


The HLVs will be moblising to the Hewett feild in on or around the 1st of April. The HLVs will be completing preparation activites, and lifting and removing the topsides and jackets in the period April to August 2026. 

See detailed map on our bulletin website

Show More

Seismic OBN Survey - Jackdaw



Adura are planning to undertake an ocean bottom node (OBN) seismic survey in the central North Sea, covering United Kingdom Continental Shelf (UKCS) Blocks 23/27, 30/1-3, 30/7-8, and Norwegian Blocks 007/11 & 001/2. The campaign will last 45 days in total but have included contingency in the event of bad weather.


Show More

Pre-decommissioning Environmental Survey - Alder Field



In preparation of decommissioning of the Alder field, pre-decommissioning environmental survey. Survey will comprise: side scan sonar (SSS) and mutli-beam echo sounder (MBES), drop camera/video, grab sampling for chemical and faunal analyses.


Show More

Freespan - PL5152



Free Span identified on the Pipeline PL 5152- 18.19m long x 1.45m High


Show More

Marine growth and mooring line survey - Alba FSU



In preparation of decommissioning (sail away) of the Alder FSU Survey will comprise: drop camera/video transects, grab sampling for of marine growth from infrastructure for analyses


Show More

Rosebank Field Drilling Operations



The Odfjell Drilling Deepsea Atlantic Mobile Drilling Rig will be conducting operations in the Rosebank field development area.


The Odfjell Drilling operated Deepsea Atlantic mobile offshore drilling rig will be conducting drilling and well operations in the Rosebank field development area over various subsea templates for a period of approximately 18 months. 

The rig will be operating on DP, therefore there will be no moorings deployed. 

Deepsea Atlantic call sign is 2CEV5. 

See detailed map on our bulletin website

Show More

Freespan - PL370 Abandoned Thames Pipeline



Free Span identified on the Abandoned Thames Pipeline PL 370 - 41.42m long x 0.83m High


Show More

Freespan - PL370 Abandoned Thames Pipeline



Free Span identified on the Abandoned Thames Pipeline PL 370 - 27.02m long x 0.83m High


Show More

Freespan - PL5152



Free Span identified on the Pipeline PL 5152 - 17.11m long x 1.54m High


Show More

Freespan - PL1331



Free Span identified on the Pipeline PL 1331- 34.1m long x 0.8m High


Show More

Freespan - PL1331



Free Span identified on the Pipeline PL 1331 - 37.6m long x 1.1m High


Show More

Freespan - PL1331



Free Span identified on the Pipeline PL 1331 - 28.5m long x 0.9m High


Show More

Freespan - PL1331



Free Span identified on the Pipeline PL 1331 - 13.7m long x 1.5m High


Show More

Freespan - PL 1331



Free Span identified on the Pipeline PL 1331 - 14.6m long x 1.9m High


Show More

WAD Umbilical Changeout - Trencher



The North Sea Enabler will be trenching along this route to aid in the installation of a new umbilical cable between the Bruce CR platform and the WAD manifold. The trencher is expected to be in the field at the earliest 05/04/26 and for 7 days.


Show More

Subsea Decommissioning Dana Western Isles



Dana Petroleum (E&P) Limited have contracted Helix Energy Solutions (Well Ops) to carryout Well Operations at Western Isles decommissioning project using the MSV Well Enhancer at the North and South Drill Centres in April 2026.


The Harris and Barra fields and located in Block 201/24a of the UKCS, 160km to the East of Shetland and apprcximately 500km North- North East of Aberdeen. The water depth in the area varies from approximatety 150msw to 165msw. The Western Isles production storage and offshore vessel (FPSO) has been been disconnected and no longer in the area. The Well Enhancer will be working on Wells at the North and South Drill Centres with ROV support, plus possible diving operations if required. There will be SIMOPS with the CSV Boka Nothern Ocean that will be in the Dana Western Isles area carryout decommissioning operations with ROV only support.

See detailed map on our bulletin website

Show More

Umbilical Changeout - Bruce CR platform and the WAD Manifold



The Seven Atlantic will be along this route installing a new umbilical cable between the Bruce CR platform and the WAD manifold. The DSV is expected to be in the field at the earliest 01/04/26 and for 21 days.


Show More

Weather Buoy Installation – Rosebank Offshore Development Area



A tethered meteorological weather buoy is installed at the given coordinates. Vessels are requested to keep safe distance.


Show More

FPSO & moorings decommissioning - Western Isles



The Western Isles FPSO and mooring lines have been removed. During 2026 the mooring piles will be cut and recovered.


The mooring piles will be cut below seabed level and the cut sections recovered.

See detailed map on our bulletin website

Show More

Western Isles infield subsea infrastructure decommissioning



Infield pipelines and manifolds associated with the Western Isles Development will be decommissioned


Risers, tie-in spools, manifolds and mid-water arches will be recovered from the seabed. The surface laid pipeline bundles serving the North and South drill centres will remain in place until a decommissioning option is finalised. Wellheads will be left in place with existing fishing protection structures subject to a separate well plug and abandonment campaign, which will commence in 2026.

New rock armour will be deposited to protect exposed pipeline bundle ends at the North and South Drill Centre and North and South Riser Base locations.

Work will re-commence from 15th March 2026.

See detailed map on our bulletin website

Show More

Noble Intrepid at BC39



Please be advised that the Jack-up rig 'Noble Intrepid' is at this location, and will remain in this position for up to 90 days.


Show More

East Brae Decommissioning works



TAQA (duty holder) of East Brae will be conducting decommissioning activities at the East Brae.


TAQA (duty holder) will be conducting decommissioning activities at the East Brae installation commencing between the 12th of May 2026 and 11th June 2026 for circa 60 days. This work will include preparation works for Topside and Conductor removals.

Vessels will be operating within the 500m safety zone of the platform and on occasion, will be at stand-by, near to the boundary of the 500m zone.

Vessels in attendance will be the Balder and Sleipner for the work scopes.

The ERRV Vos Traveller will be performing standby duties.

See detailed map on our bulletin website

Show More

Rig - Deepsea Yantai



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Swift 10



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - COSL Promoter



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Valaris Stavanger



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Show More

Rig - Seafox 4



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Danger - Protruding Isolation Plugs on End of Live Pipeline - Galahad



Following the removal of the Galahad monopod structure Perenco UK is warning mariners of protruding isolation plugs on pipeline PL1166, which is connected to the live/operational Lancelot Area Production System. An Isolated Danger Marker Buoy has been installed at the site of the former Galahad structure to mark this hazard.


Show More

DSV Activity - Thistle Platform



DSV operations within Thistle 500m zone conducting decommissioning operations.


Show More

Stena Don in Penguin Field in Northern North Sea



Stena Don in Penguin Field in Northern North Sea at Pan NW. Pre-lay anchors will be installed initially, rig will moor up immediately after anchors are installed. Rig will be on location for approximately 120 days, the anchor spread could remain until 31st October.


Show More

Subsea Decommissioning - Western Isles Locations



Dana Petroleum (E&P) Limited has contracted Boskalis Subsea Services (BSS) for the Western Isles decommissioning project using the CSV Boka Northern Ocean.


Harris and Barra fields are located in Block 201/24a of the UKCS, 160km to the East of Shetland, and apprcximately 500km North-North East of Aberdeen. The water depth in the area varies from approximately 150m to 165m. The Western Isles production storage and offshore vessel (FPSO) has been disconnected and offstation, but production trees and water injections trees via 9-off flexible risers, 2 -off dynamic umbilical's, 2 -off bundle systems with associated spools and jumpers, 2- off mid-water arches (MWA), FPSO mooring piles, concrete mattressess remain on location. Boka Northern Ocean will carryout some of the decommissioning works commencising in early April for up to 90 days on location, note only ROV's operations from the CSV Boka Northern Ocean for this part of the project.

See detailed map on our bulletin website

Show More

Planned Rig Move – Dolphin PBLJ



This is to advise of the upcoming planned rig move for the Dolphin PBLJ. The rig will relocate from the Joanne Field to the Balmoral Field to undertake P&A operations. • Departure from Joanne Field: 21 January (Estimated) • Estimated Duration on Location: Approximately 140 days • Scope: Five well P&A campaign


Show More

Rig - Transocean Norge



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Linus



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Prospector 1



This oil & gas drilling rig has moved to this new position. Rigs are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Irish Sea Pioneer



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Valaris 72



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Deepsea Nordkapp



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Noble Innovator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rigmove - Valaris 121



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Show More

Rig - Deepsea Stavanger



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Askeladden



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Noble Integrator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Askepott



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Noble Lloyd Noble



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig Move - Maersk Inspirer



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Valaris 122



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Paul B Loyd Junior



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Noble Invincible



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Ensco 92



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

Rig - Valaris 123



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Show More

204/20a Schiehallion NW Drill Centre Wet Parked Marine Riser



In Q2 2024, a Semi-submersible Mobile Offshore Drilling Unit incurred an unexpected release of the Lower Marine Riser Package, and the associated Marine Riser. This fell to seabed in the Schiehallion NW drill centre. Subsequent works were undertaken to cut the riser into manageable sections, relocate them to a wet park area outside the 500m zone at Schiehallion NW. Stabilisation material was then installed to secure their position pending retrieval to surface and subsequent on-shore disposal.


14 off Marine riser sections remain on the seabed at the location identified on the attached layout drawing. Their positioning has been secured utilising a combination of methods involving the following deployed equipment:

  • 24 off gabion bags (2 te each),
  • 24 off (6m x 3m mattresses),
  • 14 off horizontal nets and 
  • 1 off clump weight.

Plans are underway to retrieve all items during a single campaign scheduled for 2026 following which this notice will be retracted/updated to confirm full removal.

The Marine Riser was cut up, relocated and subsequently stabilised via a Marine Licence (ML/1100) issued by OPRED.

See detailed map on our bulletin website

Show More

Marine Installation Operations – Rosebank Development Area



Multiple vessels will be carrying out pipeline and subsea structure installation activities within the charted Rosebank Development Area. Other vessels are requested to keep safe distance.


Show More

Noble Innovator - Mungo



Please be advised that the Jack-up rig 'Noble Innovator' is alongside the Mungo Platform, and will remain in this position for the foreseeable.


Show More

Disclaimer

TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" BUTTON. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.

Agree and download Cancel