[ Accessibility | Jump to content]
Voir la carte
X

Actualités Offshore








Tout Danger Activité Nouvelles

Clair

Seabed Remediation - Mungo



Boka Northern Ocean will be undertaking seabed remediation works in the vicinity of the Mungo NUI to facilitate the deployment of a Jack Up Drilling Rig for future drilling operations. The dredging operations will ensure that a stable and even area is available for the spud cans to sit on. All works will be completed within the platform 500m zone.


Montre plus

Diving operations in Ninian Area



Vessel Boka Topaz operating in the Lyell, Ninian, Strathspey and Columba E fields between 07 April and 03 June, carrying out diving activities.


Montre plus

PL17 Disconnection - Cormorant Alpha PL17 SSIV and at Pelican Manifold



The Seven Atlantic will be working at Cormorant Alpha PL17 SSIV and at Pelican Manifold completing disconnection of subsea pipelines


Montre plus

Drilling underway- Appraisal well - Crosgan 42/14a-C



The Prospector 1 is now on location for 90 days in block 42/14a to drill an appraisal well.


The Prospector-1 is a self elevated jack-up rig which is now in position over the proposed well location, and is currently jacking down its legs to the seabed.  The Prospector 1 is anticipated to spend a total of 90 days at the proposed Crosgan 42/14a-C appraisal well location.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Subsea Decommissioning - Western Isles Locations



Dana Petroleum (E&P) Limited has contracted Boskalis Subsea Services (BSS) for the Western Isles decommissioning project using the CSV Boka Northern Ocean.


Harris and Barra fields are located in Block 201/24a of the UKCS, 160km to the East of Shetland, and apprcximately 500km North-North East of Aberdeen. The water depth in the area varies from approximately 150m to 165m. The Western Isles production storage and offshore vessel (FPSO) has been disconnected and offstation, but production trees and water injections trees via 9-off flexible risers, 2 -off dynamic umbilical's, 2 -off bundle systems with associated spools and jumpers, 2- off mid-water arches (MWA), FPSO mooring piles, concrete mattressess remain on location. Boka Northern Ocean will carryout some of the decommissioning works commencising in early April for up to 90 days on location, note only ROV's operations from the CSV Boka Northern Ocean for this part of the project.

Voir une carte détaillée sur notre site web bulletin

Montre plus

500m controlled zone - Abbey-2 WHPS Incomplete



The Subsea Abbey-2 WHPS (wellhead protective structure) is installed over the well, but the structure requires further work to complete. The work is planned to be completed in the spring, but in the meantime the location is to be guarded by a guard vessel, initially the Putford Terminator ERRV will maintain a controlled 500m zone around the Abbey-2 subsea well location.


Montre plus

Debris Survey - York P&A Rig



The Fugro Searcher will undertake a geophysical rig debris survey at the York location (UKCS block 47/3) in preparation for the arrival of the Well-Safe Protector jack-up rig, which will undertake P&A activities.


The Fugro Searcher will undertake a geophysical rig debris survey at the York location in preparation for the arrival of the Well-Safe Protector jack-up rig, which will undertake P&A activities.  The survey will take 1 day to complete and comprise multibeam, echosounder and side scan sonar over an area of 0.1 km2.  

Voir une carte détaillée sur notre site web bulletin

Montre plus

COSL Innovator MODU at Evelyn BE-01



Submitting a notice to make fishing vessels aware that anchors are to be pre-laid at Belinda BE-01 between 7th and 10th March 2025. MODU due on location 16th March 2025


The MODU COSLInnovator is scheduled to be on location at Belinda BE-01 location to undertake drilling operations.

Voir une carte détaillée sur notre site web bulletin

Montre plus

New Safety Zone: Victory PLEM (South), Victory Field, Block 207/1b



A new safety zone has been granted by the Secretary of State for the above location/structure. The safety zone will come into force on 25th March 2025.


Kingfisher note:

 

This safety zone may be new, or an amendment to an existing zone. It may also replace a safety zone in place around a platform, or other surface structure for the purposes of decommissioning.

 

Your FishSAFE Information will be updated in the next release.

 

Voir une carte détaillée sur notre site web bulletin

Montre plus

New Safety Zone: Victory PLEM (North), Victory Field, Block 207/1a



A new safety zone has been granted by the Secretary of State for the above location/structure. The safety zone will come into force on 25th March 2025.


Kingfisher note:

 

This safety zone may be new, or an amendment to an existing zone. It may also replace a safety zone in place around a platform, or other surface structure for the purposes of decommissioning.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

New Safety Zone: Teal West Development, Teal West Field, Block 21/24d



A new safety zone has been granted by the Secretary of State for the above location/structure. The safety zone will come into force on 25th March 2025.


Kingfisher note:

 

This safety zone may be new, or an amendment to an existing zone. It may also replace a safety zone in place around a platform, or other surface structure for the purposes of decommissioning.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

New Well "EV-02" at Dana / Sirica Evelyn Field using the DSV Seven Kestrel



Dana have contracted Subsea 7 to tied back the new Well EV-02 to the Existing Evelyn Valve Skid, using the DSV Seven Kestrel for Diving and ROV Operations for the tie-back workscope.


The DSV Seven Kestrel will be in the field in early April 2025 for about 3 weeks weather depending

Voir une carte détaillée sur notre site web bulletin

Montre plus

Geophysical & environmental surveys - Arthur and Gawain



Post decommissioning survey at the Arthur and Gawain subsea installation and the associated pipelines. The survey areas are centred on the subsea installations located within Blocks 49/29 and 53/2. The surveys comprise both geophysical survey using MBES, SSS, environmental baseline survey comprising grab sampling and DDC, and passive magnetometer.


Montre plus

Well Intervention Work - HAEVA at ST2 Ravenspurn Field



Please be advised that the HAEVA Jack-Up Barge (JUB) is due to depart from the ST3 platform at the earliest date of 27th March 2025 (dependent on weather), and transit to ST2 in the Ravenspurn Field, where it will commence Well Intervention work. The estimated earliest arrival date of the HAEVA at ST2 is 30th March 2025. The JUB will remain on location at ST2 until latest 30th June 2025.


Montre plus

OGW Rig - Schiehallion North West Drill Centre



Please be advised that the semi-sub rig Ocean Great White is now hooked up at North West DC, using the below noted mooring pattern. There are no surface buoys on site. Anchor handler vessels have departed, and the rig expects to be on site for 5 - 7 weeks.


Montre plus

Ground Moorings at Alligin Drill Centre



Seven mooring ground chain and pennant sections were recovered during the week commencing 14th October 2024, as part of the rig move to Schiehallion North. One mooring remains in place until further notice, at the below noted location. There are no surface buoys or mid-water sections.


Montre plus

Stena Don at Victory A1 Well (Pre-lays and rig position)



The Stena Don will complete drilling and completion activities at Victory A1 location. The work will take 75days (D50), 92 days (D90) and will be moored with 8 anchor lines through this time. Prior to rig arrival, pre-lays will be installed from the 12th of March. The rig is then estimated to arrive on the 20th of March.


The anchor lines extend up to 2k out from the rig.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Stena Don rig move



The Stena Don will be moving from Pierce field in the Central North Sea to Victory. The rig will stop at Scapa Flow as an intermediate location to complete logistics operations prior to contuing to Victory.


Montre plus

Overtrawl survey - Guinevere



Guinevere safety zone and pipelines overtrawl. Overtrawl survey of 500m safety zone at Guinevere and the pipelines covering a 100m corridor -50m either side up to the edge of the Lancelot 500m safety zone


Montre plus

Diving - Hewett Field



Diving will be transferring from the DSV Topaz to the Boka Da Vinci on the 18th Dec, the campaign will now go through to end of april 2025


various diving tasks in field and at V72 drill rig 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Platform Debris and Environmental Surveys - Brigantine BE,Brigantine BG,Leman BT,Leman G,Carrack Q



Gardline Ocean Researcher has been commissioned to exeucte debris and environmental surveys


The ocean Researcher will be executing surveys around the following offshore facilities:

Caravel

Brigantine BE

Brigantine BG

Leman BT

Leman G

Carrack QA

The vessel will be either towing equipment or having equipment deployed on the seabed and is therefore restricted in its manouverability. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Environmental Survey - Greater Stella Area



Pre-decommissioning environmental survey


In preparation of decommissioning of the GSA fields, pre-decommissioning environmental survey of the 5 drill centres of the GSA and wider environmental (habitats) survey across the GSA assets (pipelines/umbilical locations, including export lines and tie-ins). Survey will comprise: mutli-beam echo sounder (MBES), drop camera/video, grab/box core sampling for chemical and faunal analyses

Voir une carte détaillée sur notre site web bulletin

Montre plus

Decommissioning - Wenlock



The ERDA Jackup Barge will undertake well plug and abandonment (P&A) works at the Wenlock installation. Works will be between 13 April 2025 and 01 July 2025. This P&A works are located within the 500m exclusion zone generated by the Wenlock installation.


Montre plus

Seabed Debris - Hewett 52/5A Platform Removed



The Hewett gas installation the 52/5A has been removed - however some seabed debris will remain until final removal activities.


This notification relates to the Hewett 52/5A Installation, its removal (topsides and jacket) as part of the overall Hewett Field Decommissioning Project and the presence of debris on the seabed within the footprint and vicinity of the jacket as a legacy from its operational life (> 50 yrs). This debris has the potential to create hazards for other users of the sea, in particular trawling and fishing activities.

 

A seabed debris removal campaign will be undertaken (timing to be confirmed) to achieve and demonstrate the requirements for seabed clearance (including over trawl), as defined in the overall Hewett Field Decommissioning Programmes for surface and subsurface infrastructure.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Install and tie-in - Alligin Drill Centre West of Shetland



Subsea works at the Alligin Drill Centre (204/20a), West of Shetland. Planned works are described in the Consent to Locate Ref: CL/1487 as issued by OPRED (attached to this Notification) and the Pipeline Works Authorisation PW5143 as issued by the NSTA. Works include installation of Xmas Tree on the recently drilled Water Injection well and subsequent tie-in via jumper installation to existing infrastructure. All works will remain within the 500mz at 204/20a Alligin Subsea Drill Center.


The Schiehallion, Loyal & Alligin subsea fields (West of Shetland) are to be expended with new water injection and production wells over a campaign from 2023 to 2025, with all new wells connecting to existing subsea infrastructure. To date 3 new wells have been installed over 2023/24 with a further 3 wells to be installed in 2025.

 

As part of this phase of work, a new water injection Christmas Tree (AW12) will be tied into the existing Alligin well (AW11) flowbase, via a 6" water injection jumper, along with new controls supply jumpers (hydraulic and electrical) connected into an existing Alligin controls distribution assembly. 

 

This work scope also includes the movement of previously wet stored jumpers from a defined wet store location into the work site. This wet store location and all other activities covered within these Notifications are located fully within the subsea 500m zone surrounding the Alligin Drill Centre – locations as per attached.

 

The Normand Subsea MSV will carry out the subsea activities, scheduled to take ~6 weeks. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig Move - COSL Pioneer



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Well Safe Protector



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Metocean Buoy - Victory Development



Metocean buoy installed at the Victory development area. Buoy is floating on surface with mooring consisting of steel ballast. Note that buoy can move up to 150 m around deployment location. Deployment vessel: MS Elisabeth Duration: 6 months


Markers:

Metocean buoy

Character: Fl (5) Y 20s

Color: Yellow disc

Mooring: 3000 kg steel ballast with chain

Buoy diameter: 3 m

AIS base station address: 1328842/1/Shell Victory Wave Buoy WS154

 

 

 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Infill Drilling - Cygnus Field



The Valaris Norway is due to move into the Cygnus field between 18 March - 31st December 2025 to carry out infill drilling.


Montre plus

Diving Support Vessel (DSV) Activity at Thistle Platform



Diving Support Vessel (DSV) 'Seven Atlantic' will be performing Inspection, Repair and Maintenance (IRM) and decommissioning activities at the Thistle platform.


Montre plus

Debris Survey & Inspection - Brent Area



ROV Multibeam and Sidescan Sonar survey within Brent area. A Geophysical and visual Debris survey will be carried out by Ocean Infinity using survey vessel M/V Armada 7801. All vessels shall at all times make sure they have the AIS system turned on when approaching the Armada 7801 vessel. Work will commence in the UK waters from 7th of March 2025 until approximately 7th of April 2025.


During the survey the vessels M/V Armada 7801 will be using a Work Class ROV (WROV), equipped with Multibeam Echosounder (MBES), Side Scan Sonar (SSS) and video cameras. The WROV will be ~200 m from the vessel and about 1-5m above seabed, at which such times, the survey vessel has restricted ability to manoeuvre and approaching vessels are requested to pass at a safe speed and distance.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Hazard - Forvie Manifold



Potential new snag hazard observed at subsea protection structure over the Forvie Manifold. Structure sits at center of the subsea 500m zone. Vessels requested to stay well clear of 500m zone.


Montre plus

Obstruction - Well 44/21-1



Following on from a Survey. An obstruction has been identified, it is believed to be less than 1m above the seabed. It is advised to avoid the location until this has been resolved.


There is no recorded infrastructure within this area. There is an Abandoned Phase 3 wellbore within the area of this obstruction.

 

The surveying company will complete another survey in the near future to visualise the obstruction better, but this is not confirmed yet. In the meantime we would like to make you aware as we believe this obstruction is not currently recorded on any admiralty charts.  

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig - Swift 10



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Deepsea Stavanger



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Noble Innovator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Unmarked and unguarded - Southwark Platform



The Southwark platform has suffered a loss of power. The attendant Guard Vessel may be unable to maintain safe station keeping during periods of poor weather / Storm conditions. For short periods the platform may be unguarded and unlit


Montre plus

Liverpool Bay Area Boreholes - Dina Polaris



Two boreholes inside Douglas and 4km south of Hamilton Platform


Two boreholes inside Douglas and 4km south of Hamilton Platform 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Exposed pipeline at PL2557 cut-off



Exposed pipeline at PL2557 cut-off location which presents a snagging hazard.


Rock placement previously covering PL2557 cut-off location is no longer in place. Exposed cut-off pipeline presents a snagging hazard on the seabed.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Pre-laid anchors at Utgard location



Prelaid anchors for Deepsea Atlantic at Utgard location


Anchors prelaid according to attached drawings.

System consists of anchor, with bottom chain of prox 1000 meters. Laid down on seafloor complete with light rov pick up system.

 

Total of 8 x anchors and lines installed but only 3 x anchors and lines inside UKCS. Attached pdf shows NCS anchors and lines.

 

An exclusion of 2200 meters radius from the centre (rig position) is requested.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig - Transocean Norge



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Shelf Drilling Winner (ex Noble Sam Turner)



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Seafox 4



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

PL24 Cut-point Freespan - North Sea



The cut-point of PL24 is exposed and is protruding significantly from the seabed; approximately 18m long and 6m high. This creates an increased risk of snagging of trawling equipment, or similar, compared to a regular freespan.


The cut-point of PL24 is exposed and is protruding significantly from the seabed; approximately 6m from the seabed at its highest point and overhanging approximately 18m long from where the line makes contact with the seabed again. This creates an increased risk of snagging of trawling equipment, or similar, compared to a regular freespan.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig - Noble Reacher (ex Maersk)



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Development Project - Victory Field



The Victory Project is to develop the Victory subsea gas field as a single well tie-back to the Shetland Gas Plant. This is to be achieved by drilling a new well and installing a pipeline to route hydrocarbons via an existing hot tap tee into the existing Greater Laggan Area (GLA) pipeline system to export via the Shetland Gas Plant. Well control will be provide via an umbilical pipeline route from Edradour manifold location to the Victory Well.


Note: the Victory wellsite is within an Offshore Development Area and as such, it is advised not to fish within an ODA because of potential construction activities.

 

Vessel Plan for 2025

 

Vessel Name

Location

Arrival

Departure

Activity

Stena Don

Victory

01/04/2025

15/06/2025

 

Deep Arctic

Victory

14/05/2025

30/06/2025

(TotalEnergies operated)

HTT1-2 Hot-tap operation

HTT1-2 Protection structure installation

Skandi Africa

Victory

24/06/2025

20/07/2025

Umbilical installation

Flexible flowline wet/storage

Replace Edradour GRP

Frame installation at Edradour

(Guard vessel)

Victory

30/06/2025

18/09/2025

 

(Guard vessel)

Victory

02/07/2025

17/09/2025

 

(Guard vessel)

Victory

08/07/2025

18/09/2025

 

Deep Arctic

Victory

03/08/2025

23/08/2025

Victory rigid spool installation

Flexible tie-in

Nordnes

Victory

05/09/2025

20/09/2025

Rock installation on umbilical

Rock installation on flexible

(Rock installation vessel)

Victory

TBC

TBC

(TotalEnergies operated)

Rock installation on GLA pipeline near HTT1-2

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig - COSL Promoter



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Deepsea Aberdeen



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Stena Don MODU Move And Operations - Pierce Field



Operations with Stena Don MODU at 2 mooring locations at the Pierce field. Please note the anchors and the associated lines extend outwith the MODU 500m zone.


Montre plus

Ground Moorings - Schiehallion North Drill Centre



5 mooring ground chain and pennant sections were recovered during the week commencing 20th January 2025, as part of the rig move to Schiehallion North West. Three moorings remain in place until further notice, at the below noted locations.


Montre plus

Rig - Noble Resolute (ex Maersk Resolute)



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Noble Lloyd Noble



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Ensco 92



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

E&A well abandonment campaign



Dismantling infrastructure on 12 Exploration & Appraisal wells to achieve Abandonment Phase 3 status.


The vessel is the Royal Wagenborg MSV Kingsborg. The schedule is from 19th February to 30th April.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Irish Sea in Combined Operation with the Hamilton Platform



Irish Sea Pioneer Rig Move from Hamilton North Platform to the Hamilton Platform (Liverpool Bay) completed. Irish Sea Pioneer now in combined operation with the Hamilton Platform


Will be in combined operations (COMOPS) for approximately 110 days supporting Pipe Line Pigging Operations, Well Interventions and Maintenace activities. Rigs are protected by a 500m safety zone.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Freespan - PL1339 Interconnector Pipeline



Free Span identified on the IUK Pipeline PL 1339. 65mtrs length x 1.2m height


Exposed Pipeline at the following location.

 

Emergency Remediation plan in progress

 

Notice issued on behalf of Interconnector (IUK)

Voir une carte détaillée sur notre site web bulletin

Montre plus

Metocean Survey - Clair Ridge Are



bp is planning to carry out metocean survey activities within the Clair area. Near seabed current data and associated parameters will be collected over an initial period of 12 months. The survey will be undertaken using an MPV and the total survey time is expected to be 3 days for deployment and 365 days for survey activities. The survey operations will involve the placement seven metocean deployments with moorings on the seabed that will remain in place for a year.


Between 24/09 and 27/09, the seven laid metocean buoys were recovered, serviced and redeployed at the same target location. Further, the Metocean 5 deployment was fitted with an additional current meter such that the deployment height will increase from 13m to 34m above the seabed. 

 

The buoys will remain in place until ~June 2025, at which date they will be recovered.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Injection Trials - Leman 27H



Please be advised that the ERDA Jack-Up Barge (JUB) is due to transit to Leman 27H (UKCS Block 49/27) in the Leman Field, where it will support with upcoming CCS trials. The estimated earliest arrival date of the ERDA at Leman 27H is 29th December 2024. The JUB will remain on location at Leman 27H until latest 31st March 2025.


Montre plus

V120 at Judy Riser Platform



Harbour Energy are performing a drilling campaign using the V120 Jack-Up drilling at the Judy Riser Platform location in block 30/07a. The Judy installations have a dedicated Emergency Response and Rescue Vessel (ERRV) on location monitoring the surrounding area.


Montre plus

Rig - Noble Invincible



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valaris 72



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Prospector 1



This oil & gas drilling rig has moved to this new position. Rigs are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Revoked Safety Zone: Curlew B—Wellhead



A safety zone for the above location/structure has been revoked (will no longer be enforced) by the Secretary of State. This will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may have been replaced by a new zone, or other zones may exist in the vicinity.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Revoked Safety Zone: Wellheads and manifold, Block 211, Don Field



A safety zone for the above location/structure has been revoked (will no longer be enforced) by the Secretary of State. This will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may have been replaced by a new zone, or other zones may exist in the vicinity.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Revoked Safety Zone: Athena Manifold Centre, Block 14/18b, Athena Field



A safety zone for the above location/structure has been revoked (will no longer be enforced) by the Secretary of State. This will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may have been replaced by a new zone, or other zones may exist in the vicinity.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Revoked Safety Zone: Athena Riser Base, Block 14/18b, Athena Field



A safety zone for the above location/structure has been revoked (will no longer be enforced) by the Secretary of State. This will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may have been replaced by a new zone, or other zones may exist in the vicinity.

 

Your FishSAFE Information will be updated in the next release.

 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Revoked Safety Zone: Schooner, Block 44/26a



A safety zone for the above location/structure has been revoked (will no longer be enforced) by the Secretary of State. This will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may have been replaced by a new zone, or other zones may exist in the vicinity.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

New Safety Zone: Victory Development, Victory Field, Block 207/1a



A new safety zone has been granted by the Secretary of State for the above location/structure. The safety zone will come into force on 24th December 2024.


Kingfisher note:

 

This safety zone may be new, or an amendment to an existing zone. It may also replace a safety zone in place around a platform, or other surface structure for the purposes of decommissioning.

 

Your FishSAFE Information will be updated in the next release.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Freespans along Fulmar Gas Line



Freespans, not greater than Kingfisher critical span reporting criteria but potential hazard. These will be monitored over time. Next inspection planned in Q4 2024.


Montre plus

Plug and Abandonment Operations - UMC wells



Noble Patriot to complete plug and abandonment operations at the UMC wells. Positioned with 8 x GBAs within 500m radius of 61 09.44' North 01 06.44' East.


Noble Patriot to complete plug and abandonment operations at the UMC wells.  Positioned with 8 x GBAs within 500m radius of 61 09.44' North 01 06.44' East. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Structure in situ - Leverett CAN



Leverett CAN-basic left in situ until it is recovered by a vessel. Following the drilling of the Leverett appraisal well, the Transocean PBLJ and its anchors left the location on 14th February. The Leverett CAN-basic structure will remain in situ at the well location until it is recovered.


Recovery of the CAN-basic structure is now planned for summer 2025. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Offshore Development Area - Penguins Redevelopment Project



The project includes extending the life of the existing wells and addition of eight new wells. The new wells will be tied into the existing Penguins infrastructure and connected into a new FPSO. The pipeline system will be split into a North and South production pipeline, with the FPSO positioned close to the centre of the field. An offshore development area has been granted on the 18th April 2024 to further protect the pressurised infrastructure during the ongoing construction phase.


UKCS Block ID: 211/13a and 211/14a 

Water Depths refer to Lowest Astronomical Tide (LAT) with all depths quoted in metres. 

No visible marker (marker buoys) will be deployed. 

Schematic drawing has been attached.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Offshore Development Area - Victory Development



The Victory Project consists of the development of the Victory Subsea gas field as a single well tie-back to the Shetland Gas Plant. An Offshore Development Area has been put in place during the construction phase based upon the planned location of the Victory PLEM (North) between May 2024 and September 2025.  The offshore development area for Victory Project was granted on the 20th March 2024. (see Schematic drawing att.)


UKCS Block ID: 206/4a, 206/5c and 207/1a

Water Depths refer to Lowest Astronomical Tide (LAT) with all depths quoted in metres – 126m – 296m

No visible marker (marker buoys) will be deployed.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Jackdaw Development - North Sea



The Jackdaw field is an ultra-high pressure/high temperature (uHPHT) reservoir that will be developed with a not permanently attended Wellhead Platform (WHP). Four wells will be drilled at the Jackdaw WHP. Produced fluids will be exported via a subsea pipeline to the Shearwater platform where these will be processed before onward export via the Fulmar Gas Line and the Forties Pipeline System. Vessels: SUV1/Deep Discoverer/Deep Energy/Normand Drott /SUV2 (Olympic Trition).


Jackdaw Installation 2024/2025

New Riser installed to Shearwater A using DSV.

New pipeline will be installed between Shearwater A and Jackdaw.

New SSIV will be installed within the Shearwater 500m zone using DSV or CV.

New electro-hydraulic/chemical umbilical & associated protection material will be installed between Shearwater C and new Shearwater SSIV using DSV.

New SSIV will be installed within the Jackdaw 500m zone using DSV or CV.

New electro-hydraulic/chemical umbilical will be installed between Jackdaw wellhead Platform and New Jackdaw SSIV using DSV.

New tie-in spools & associated protection material will be installed between new pipeline and Jackdaw riser via new SSIV using DSV.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Seabed hazards following removal of Banff FPSO anchors & moorings



Trenches at mooring line touchdown points - remediated with rock placement.


10 mooring line trenches, cut into the clay seabed. Remediation of these trenches has been completed (by rock infill to a profile below mean seabed), although seabed verification has not yet been carried out.

Voir une carte détaillée sur notre site web bulletin

Montre plus

Rig - Askepott



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Linus



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valaris 248 (ex Gorilla VI)



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valaris 122



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Seafox 7



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig Move - Maersk Inspirer



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Noble Intrepid



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig Move - Shelf Drilling Fortress



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Noble Integrator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valris 72



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Maersk Innovator



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - West Elara



This oil & gas drilling rig has moved to this new position. Rigs are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valaris 120



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Montre plus

Exposed section and mattress at PL1877 - Telford



Concrete mattress in open water identified during ROV survey as dislodged from Telford PL1877. Small section of pipeline exposed.


During a recent ROV survey, it was discovered that a mattress has become dislodged at PL1877 between Telford central and Telford east manifold outwith either 500m zone. This has left approximately 6m of the pipeline uncovered. CNOOC are currently endeavouring to resolve this issue with both interim and long-term solutions identified. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Disconnection - Brent WLGP (PL17)



This scope of work is to flood the Cormorant Alpha to WLGP SSIV production pipeline PL17, before cutting and recovering a short section within the NL-WL PLEM 500m safety zone, as part of a series of works to de-energise Cormorant Alpha. Vessel Name: Seven Atlantic


Montre plus

Rig - Askeladden



This oil & gas drilling rig has moved to this new position. Rig are protected by a 500m safety zone and some may have anchors extending beyond this zone.


Montre plus

Rig - Valaris Stavanger



Oil & gas rigs are protected by a 500m safety zone and some may have anchors extending hundreds of metres outside this zone.


Montre plus

Rig Move - Dolphin PBLJ to Brodgar field



Harbour Energy are scheduled to complete Drilling operations (using the Dolphin Paul B Loyd Junior – Semi Submersible) at Gilderoy 15/28b- and then move the rig to the Brodgar field in the Central North Sea block 21/03a. This move is currently planned for the 01/11/24.


Montre plus

Well Intervention Work - HAEVA at ST3 Ravenspurn Field



Please be advised that the HAEVA Jack-Up Barge (JUB) is due to depart from the Arthur subsea manifold on 30th September 2024 (at the earliest and dependent on weather), and transit to ST3 (UKCS 42/30) in the Ravenspurn Field, where it will commence Well Intervention work. The estimated earliest arrival date of the HAEVA at ST3 is 1st October 2024. The JUB will remain on location at ST3 until latest 31st March 2025.


Montre plus

Subsea Seismic Nodes - Leman Field



Please be advised that 12 retrievable nodes will be deployed on the seabed in the Leman Field as part of upcoming spot seismic survey.


12 retrievable nodes will be deployed on the seabed for the duration of upcoming seismic survey - their deployment is anticipated from October 25th 2024 until March 31st 2025. These nodes are 1m x 1m in size, the ballast weighing 26kg with a 10kg bouyant. These nodes will not be marked by a surface buoy. 

Voir une carte détaillée sur notre site web bulletin

Montre plus

Valaris V121 over Shearwater Alpha



Valaris V121 MODU jack-up rig will be situated over Shearwater Alpha platform. Valaris V121 MODU will be on location at Shearwater until June 2026.


Montre plus

Disclaimer

TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" BUTTON. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.

Accepter et télécharger Annuler
The website stores some data in your browser. We do not store any personal information. By clicking 'OK', you accept this. See our terms and conditions. OK